Mumbai-Ahmedabad, Bullet Train
The Financial Express · 1d
Mumbai-Ahmedabad Bullet Train Project Advances: Foundation work for eight stations in Gujarat now complete
As of now, 350 kilometers of pier foundations, 316 kilometers of pier constructions, 221 kilometers of girder casting, and 190 kilometers of girder launching have been completed.
Swarajya · 9d
Mumbai-Ahmedabad Bullet Train Corridor Fitted With 175,000 Advanced Noise Barriers So Far
Internally, the bullet train’s double-skin aluminium alloy body minimises noise levels for passengers. Additionally, its streamlined nose design significantly reduces aerodynamic drag, thereby mitigating the loud sounds produced by micro-pressure waves as the train exits tunnels.
The Free Press Journal · 10d
Mumbai-Ahmedabad Bullet Train Corridor Sees Installation Of 1.75 Lakh Noise Barriers
"The installation of noise barriers work along the Mumbai-Ahmedabad Bullet Train Corridor is underway. As of date, the noise barriers have been installed over a stretch of 87.5 km. More than 1,75,000 noise barriers have been installed in Gujarat" said an official.
devdiscourse · 7d
Ministers Visit Mumbai-Ahmedabad Bullet Train Project: Major Milestones in Engineering and Finance Unveiled
Officials from Maldives visited the Mumbai-Ahmedabad bullet train construction site, inspecting a 7 km high-speed rail tunnel. Realty developer Purvankara secured redevelopment rights in South Mumbai,